Fig. Figure 1 shows the organization of the workplace, the installation site fencing, border earthworks most recessed well SGR-MH-104. Mark the bottom of the excavation of the pit + 97.14.Pri existing ground elevation +99,600 depth of excavation 2.46 metra.Prinyato two slope at a height of 1.23 meters. At a distance of 1 meter from the slope set strict guard.