We got the project hakidysh Congress Centre which is confirmed 100% works. According Hakidysh for work performed on the project sum payment of 311,925 US dollars. Whereas the cost of the contract is 391 925 US dollars.
When calculating hakidisha by Polimex considered a supplementary agreement to reduce the cost of 100 000 US dollars.
Thus the amount of underpayment of the contract is 80 000
Calculation Hakidishe made without taking into account the additional agreement on 2 more units